| Year |
Work Completed |
Workers |
Hours |
Total Hours |
Owner Savings |
Owner Savings |
Owner Savings |
Owner Savings |
|
|
|
|
|
|
|
|
| 2008 |
Fence repair |
|
|
|
|
|
|
| Fall |
Ceiling repair building 3, unit 204 |
|
|
|
|
|
|
| |
Concrete ceiling and rust repairs - garage area building 5 |
|
|
|
|
|
|
| |
Stairway paint touch up |
|
|
|
|
|
|
| |
Stairway panel and clip repair |
|
|
|
|
|
|
| |
Deck touch ups |
8 |
5 |
40 |
######## |
|
|
|
|
| Spring |
Power washed building 3 stairs as prep for painting |
|
|
|
|
|
|
| |
Removed the dead tree from the front of building 4 |
|
|
|
|
|
|
| |
Clean up around the buildings and dumpster areas |
|
|
|
|
|
|
| |
Installation of additional landscape 6x6 timbers for buildings
3 & 5 |
|
|
|
|
|
|
| |
Power washed all three garage areas |
|
|
|
|
|
|
| |
Touched up the white garage ceilings and walls |
|
|
|
|
|
|
| |
Painted the wood plumbing pipe boxes in all three garage areas |
|
|
|
|
|
|
| |
Mulched flower beds in all three buildings |
|
|
|
|
|
|
| |
Reparied the trash enclosures for buildings 4 & 5 |
|
|
|
|
|
|
| |
Planted flowers in front of building 4 |
|
|
|
|
|
|
| |
Touched up the brown paint on the steps and railings in
buildings 4 & 5 |
|
|
|
|
|
|
| |
Evaluated a plumbing drain leak in the east garage bay of
building 5 |
32 |
6 |
192 |
|
|
|
|
|
| |
Total |
|
232 |
$ 12,992 |
|
$ 12,992 |
|
|
| 2007 |
Yellow parking blocks repainted |
|
|
|
|
|
|
|
|
|
|
|
| Fall |
Garage parking spaces relined |
|
|
|
|
|
|
|
|
| |
Buildings
3 & 5 roof hatches repaired, remounted and reinforced |
|
|
|
|
|
|
|
|
| |
Buildings 3, 4 & 5 roof hatches primed and painted |
|
|
|
|
|
|
|
|
| |
Buildings 3, 4 & 5 roofs inspected and debris removal |
|
|
|
|
|
|
|
|
| |
Roof seams re-tarred and rotten beam replaced |
|
|
|
|
|
|
|
|
| |
Building 4 leaking spigot repaired |
|
|
|
|
|
|
|
|
| |
Missing
and burned out light bulbs replaced |
|
|
|
|
|
|
|
|
| |
Rain spouts
cleaned out and re-secured |
|
|
|
|
|
|
|
|
| |
General clean up of flower beds |
|
|
|
|
|
|
|
|
| |
Miscellaneous painting |
11 |
8 |
88 |
|
|
|
|
|
|
|
| Spring |
New shed assembled and installed on new foundation |
|
|
|
|
|
|
|
|
| |
Flower beds weeded and mulched |
|
|
|
|
|
|
|
|
| |
New flowers planted and trees/shrubs trimmed |
|
|
|
|
|
|
|
|
| |
Parking block numbers repainted |
|
|
|
|
|
|
|
|
| |
Parking number signs switched for space rotation |
|
|
|
|
|
|
|
|
| |
Replacement of metal clips on electrical conduit |
|
|
|
|
|
|
|
|
| |
Stairs touched up in all three buildings |
|
|
|
|
|
|
|
|
| |
General clean up |
|
|
|
|
|
|
|
|
| |
Painting of back fence, posts and rails |
|
|
|
|
|
|
|
|
| |
Removal of parking block that was too close to building 5 |
|
|
|
|
|
|
|
|
| |
Repair and insulation of open holes in garage ceilings |
|
|
|
|
|
|
|
|
| |
Repair and straightening of conduit on building 5 |
28 |
8 |
224 |
|
|
|
|
|
|
|
| |
Totals |
|
|
312 |
$ 17,472 |
|
|
$ 17,472 |
|
|
|
|
| 2006 |
Touch-up painting of back fence |
|
|
|
|
|
|
|
|
| |
Touch-up painting of steps on each building |
|
|
|
|
|
|
|
|
| |
Touch-up painting where old signs removed |
|
|
|
|
|
|
|
|
| |
Painting of electrical boxes Buildings 3, 4 & 5 |
|
|
|
|
|
|
|
|
| |
Conduit
clip replacement Buildings 3 & 5 |
|
|
|
|
|
|
|
|
| |
Conduit painted Building 5 |
|
|
|
|
|
|
|
|
| |
Electric box hinges sealed with clear sealer |
|
|
|
|
|
|
|
|
| |
Place hinges and clasp on Building 3 water shut off door |
|
|
|
|
|
|
|
|
| |
Concrete steps sealed |
|
|
|
|
|
|
|
|
| |
Parking light on Building 5 replaced |
|
|
|
|
|
|
|
|
| |
Parking light on Building 3 serviced |
|
|
|
|
|
Saved |
|
|
| |
Replaced Thermostat and box for heat tape on Building 5 |
|
|
|
|
|
|
|
|
| |
Installed Shipley Management signs on Buildings 3 & 5 |
16 |
8 |
128 |
$
7,168 |
|
|
|
|
|
|
| |
Repaired
holes in building 5 stairwell walls |
3 |
4 |
12 |
$
672 |
|
|
2008 |
$ 12,992 |
|
|
| |
Changed
parking sign blocks and renumbered spaces |
1 |
2 |
2 |
$
112 |
|
|
2007 |
$ 17,472 |
|
|
| |
General
weeding, mulching and clean up |
4 |
7 |
28 |
$
1,568 |
|
|
2006 |
$ 11,704 |
|
|
| |
Parking lot stones and grading |
5 |
3 |
15 |
$
840 |
|
|
2005 |
$ 11,144 |
|
|
| |
Touched
up paint in stairs for building 3 & 4 |
4 |
6 |
24 |
$
1,344 |
|
|
2004 |
$ 12,208 |
|
|
| |
Totals |
|
|
209 |
$ 11,704 |
|
$ 11,704 |
2003 |
$
2,240 |
|
|
| 2005 |
Installed
new light fixtures in garage areas |
2 |
4 |
8 |
$
448 |
|
|
Total |
$ 67,760 |
|
|
| |
Repaired wind damaged roof hatch in building 5 |
3 |
1 |
3 |
$
168 |
|
|
|
|
|
|
| |
Painted roof hatch
areas |
3 |
4 |
12 |
$
672 |
|
|
|
|
| |
Board
walks for shower areas |
2 |
4 |
8 |
$
448 |
|
|
Assumptions |
|
|
| |
Railing boards |
3 |
8 |
24 |
$
1,344 |
|
|
$
40.00 |
Hourly Base Rate |
|
|
| |
Painting 2 buildings
touch up |
2 |
8 |
16 |
$
896 |
|
|
40% |
Mgmt Fee |
|
|
| |
Paint Building 5 Steps |
4 |
16 |
64 |
$
3,584 |
|
|
$
56.00 |
Total Hourly Rate |
|
|
| |
Landscaping and
mulch |
2 |
8 |
16 |
$
896 |
|
|
|
|
| |
Electric box shingles |
2 |
6 |
12 |
$
672 |
|
|
|
|
| |
Painting parking
blocks |
2 |
3 |
6 |
$
336 |
|
|
|
|
| |
Changing
numbers and signs |
2 |
1 |
2 |
$
112 |
|
|
16 people in sept and nov |
|
|
| |
Power
washing |
2 |
8 |
16 |
$
896 |
|
|
|
|
| |
Treating
landscaping ties |
2 |
4 |
8 |
$
448 |
|
|
Touch-Up Painting of back fence |
|
|
| |
Treating concrete
steps |
2 |
2 |
4 |
$
224 |
|
|
Touch-Up Painting of steps on each building |
|
|
| |
Totals |
|
|
199 |
$ 11,144 |
|
$ 11,144 |
Touch-Up Painting where old signs removed |
|
|
| 2004 |
Painted
new lines for parking spaces in garage areas |
1 |
4 |
4 |
$
224 |
|
|
Touch-Up Painting of electrical boxes |
|
|
| |
Producing new number
signs |
2 |
8 |
16 |
$
896 |
|
|
Conduit
metal clips replacement and Conduit straightening ( front of |
|
|
| |
Changing numbers and
signs |
2 |
1 |
2 |
$
112 |
|
|
Buildings III and V ) |
|
|
| |
Tree removal
Building 3 |
4 |
4 |
16 |
$
896 |
|
|
Conduit painted ( front of Building V ) |
|
|
| |
Garage area box
construction |
4 |
12 |
48 |
$
2,688 |
|
|
Electric Box hinges sealed with clear sealer |
|
|
| |
Garage powerwashing & painting |
8 |
16 |
128 |
$
7,168 |
|
|
Place hinges and clasp on Building III water shut off door |
|
|
| |
Hindge replacement |
2 |
2 |
4 |
$
224 |
|
|
Concrete steps sealed |
|
|
| |
Totals |
|
|
218 |
$ 12,208 |
|
$ 12,208 |
Parking light on Building V replaced |
|
|
| 2003 |
Parking lot stones and grading |
2 |
4 |
8 |
$
448 |
|
|
Parking light on Building III serviced |
|
|
| |
Tree removal - Buildings 4 and 5 |
8 |
4 |
32 |
$
1,792 |
|
|
Replaced Thermostat and box for heat tape on Building V |
|
|
| |
Totals |
|
|
40 |
$
2,240 |
|
|
$ 2,240 |
Installed Shipley Management Signs on Buildings III and V |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|